Sandhurst Music on Fire

Go Back to Projects

Project Overview

The event, hosted by the Army Benevolent Fund runs for three nights and features popular and classical music interspersed with firework displays and projections

ES Global’s Role – To provide an orbit stage for the 100 piece orchestra and 100 piece voice choir and a structure for the Royal Box. Project management services were also supplied by ES Global

Project Title -Sandhurst Music on Fire
Client – Army Benevolent Fund
Engineers -Robin Marks
Location -Surrey, UK
Project Value -£145,000
Project Duration – 16 days
Project Completion – September, 2008
External Footprint Area for the Orbit Stage -442.5m²
External Footprint Area for the Royal Box – 876m²
Internal Deck Area for the Orbit Stage – 380.64m²
Internal Deck Area for the Royal Box – 864m²
Build Period -9 days
Dismantling Period -3 days
Construction – Superstructure 1 system with clear and black roof sheets for the Royal Box. Standard orbit stage with 3 bays and Pros arch with clear sheets