Project Overview

Organising Committee for the 2010 Delhi Commonwealth Games required a company to supply, install, maintain and remove overlay for the Rugby 7’s event at Delhi University

ESGA JV’s Role – ESGA JV D’Art Indo was contracted to project manage the entire overlay process through design, install, maintenance and removal from a delivery, commercial and contractual perspective. The company also provided design management across multi disciplines, contractors and third party packages of work. Site management was provided to ensure timely delivery and full compliance with health and safety processes

Project Title – Supply, installation, testing, commissioning, operation, maintenance, decommissioning and removal of Games Overlay for 2010 Delhi Commonwealth Games

Client – 2010 Delhi Commonwealth Games Organising Committee
Designers – ES Global
Engineers – ES Global
Location – Delhi, India
Project Value – £14 million
Project Duration – 6 months
Project Completion – October 2010
Build Period – 2 months
Dismantling Period – 3 weeks