Project Overview

To open the Abu Dhabi Gulf Cup 2007, HQ Creative needed a system which enabled performers to be flown from outside the Zayed Sports City Stadium into the arena during the show

ES Global’s Role – ES Global supplied eight 72m high freestanding towers to support a cable net and circular truss, which was suspended over the centre of the pitch

Project Title – Abu Dhabi Gulf Cup
Client – HQ Creative
Engineers – Buro Happold
Location – Abu Dhabi, United Arab Emirates
Project Value – £1.2 million
Project Duration – 4 weeks
Project Completion – January, 2007
Build Period – 2 weeks
Dismantling Period – 1 week
Construction – ES Global steel truss and rigging